1786 Views |
TCC Sukhothai (Sugar/Hybrid/Bio Energy)
API have been entrusted with the production of electrical cabinets and installation work for the new factory.
Total Project Sales : 120 MB
Project period : April 2022 to December 2022
Project : MV and LV Switchgear Panel for Powerplant
Detail as :
-6.6kV Switchgear Panel
-400V MDB Panel
-400V MCC Panel
-Test & Commissioning at Site